RSN Engineering and Construction (RSNECC) is a leading and Global EPC (Engineering, Procurement and Construction) company.
Project No | Scope Of work | Client |
---|---|---|
EU-160 | Engineering Services For Fresh Firewater Storage Tank At Nao Tank Farm | |
EU-159 | Adequacy Checking Of Existing Heat Exchanger Supporting Structure & Its Foundation | QAFCO |
EU-154 | Engineering Service Of Temporary Structural Steel For Rg Boiler | QAFCO |
EU-152 | Engineering Services For Design Of Basket | QG |
EU-147 | Epic Of Workshop Modification And Other Miscellaneous Works For Grp In Dukhan | |
EU-145 | Engineering Services For Access Platform & Interconnecting Platform At Cdr | QAFAC |
EU-130 | Design Of Vent Size (Gasoline) | |
EU-118 | Design Verification Of Spreader Bar Design | |
EU-141 | Epic For Portable Water Supply At Dukhan – Temporary Shoring Arrangement | M/s QP |
EU-139-V1 | ||
EU-138 | Design Of Frac Tank | M/s QCHEM |
EU-137 | Designing Of Foundation Drip Ring For Storage Tank Repair | M/s QVC |
EU-136 | Design Of Temporary Supporting Structure For Heat Exchanger At Qafco | M/s QAFCO |
EU-134 | Hydralic Analysis For Pipeline | M/s QP |
EU-124A | Engineering Services For Installation Of Server Containers At Al-Jazeera Network - Varation | M/s. QATAR SITE & POWER |
EU-135 | Engineering Services For Installation Of New Crane In The Existing Fabrication Shop | M/s TRAGS |
2863 | Epic Of Hvac System In Polyethylene Mcc Building During 2017 Turnaround At Q Chem | M/s QCHEM |
EU-129 | Epic Of Mechanical Pcr Gpo (M) /1 6 / 536 Interim Supply Of Lpg From Ngl To Qpr At Ngl Plants, Mesaieed | M/s QP |
EU-127 | Engineering Services For Hazardous Material Storage Area | M/s QAFAC |
EU-124 | Engineering Services For Installation Of Server Containers At Alâ€Jazeera Network | M/s. QATAR SITE & POWER |
EU-121 | Epic For Decommissioning And Removal Of 12"Mppl And 13 Kms Of 30"Gas Pipeline | M/s. QP |
EU-120 | Npp 0050 †Engineering Services For Stress Analysis And Hydralic Calculation For Land & Marine Fuel, Drain Water Lift Station System And Foul Water Collection System | M/s. L&T |
EU-119 | Finite Element Analysis For Grp Cover For Tse Tank | M/s. STATE OF QATAR |
EU-115 | Epic For Temporary Electrical Power Bridgeing In Qg1-Civil Works | M/s. QG |
EU-114 | Design & Engineering Services For Various Civil Works At Flow Assurance Expansion Project | M/s. RAS GAS |
EU-109 | Engineering Services For Installation Of Permanent Foot Bridges And Pedestrian Gates | M/s. QG |
EU-108 | Engineering Services For Stress Analysis, Steady State And Surge Analysis | M/s. L&T |
EU-107 | Engineering Services For Temporary Support For Barzan Pipe Line | NEW PORT PROJECT |
EU-106 |  Engineering Services For Design Of Spreader Bar | M/s. QCHEM |
EU-105 | Load Calculation For Temporary Structure In Replacement Of Super Heater | - |
EU-103 | Epc For Flare Sampling Cabinets On Wet Gas, Dry Gas, Sour Gas And Spare Flare Gas Lines | M/s. QG |
EU-102 | Calculation For Beam Moment Connection For Cable Tray Support | M/s QATAR GAS |
EU-101 | Engineering Services For Heat Exchanger Support At Train 3 | M/s QATAR GAS |
EU-100 | Engineering Services For Redundant Equipment Demolition Project | M/s. QAPCO |
EU-99 | Engineering Design Verification For 400t Capacity Trussed Crane | - |
EU-98 | Engineering Services For Fire Suppression Sprinkler System For Rlpc Warehouse | M/s RAS LAFFAN POWER COMPANY |
EU-97 | Engineering Service For Stress Analysis For Plumping Systems | M/s. STATE OF QATAR |
EU-96 | Epic For Installation Of Flammable And Toxic Gas Detectors At Rlc Buildings | M/s. QATAR PETROLEUM |
EU-94 | Engineering Service For Stress Analysis For Land Fuel Systems | M/s. STATE OF QATAR |
EU-088 | Qchem-Engineering Services For Structural Platform For Flow Totalizer | |
EU-086 | Kahramaa-Mekaines Rps & Associated Pipelines Mto Preparation | |
EU-085 | Engineering Services For Temporary Storage Tank For Crude Oil Sludge | |
EU-084 | Epic Of Two Combined Projects In Qg2 (Project 2) | |
EU-083A | Engineering Services For Hmc 306b Simulation Center Structure Steel Frame (Variation) | |
EU-083 | Engineering Services For Hmc 306b Simulation Center Structure Steel Frame | |
EU-081 | Engineering Services For Selection Of Spring Support | |
EU-079 | Epic For Three Combined Projects In Laffan Refinery And Qg1 Asset | |
EU-078 | Rlic Substation For Baker Huge Storage & Blending Facility | |
EU-077 | Epic Of 12’ Jump Over For Jet A1 & 16†Jeta 1 Pipe Line From Qp To Hia | |
EU-076 | Ecs For Detailed Design Engineering For Pcr- 397 Ngl-3 Plant | |
EU-075 | Engineering Services For Replacenent Of Dolphin Hook | |
EU-074 | Epc Service For Upgrading Fixed Elevated Firewater Monitors In Train 1/2/3 | |
EU-073 | Epic For Decommissioning And Removal Of 12inch Mppl And 13km Of 30inch Gas Pipeline ( Hazop And Hazid Study) | |
EU-072 | Design Of Temporary Support Structure For Heat Exchanger | |
EU-069 | Replacement Of Damaged Sea Water Lines Of Train 2 (Qg1) | |
EU-068A | Epic For Relocation Of 48" Butterfly Valve In Sea Water Line And Facilitate Isolation(Variation1) | |
EU-068 | Epic For Relocation Of 48" Butterfly Valve In Sea Water Line And Facilitate Isolation | |
EU-067 | Replacement Of Pipe (Potable Water Line-Grp) With Ss At Rlpc | |
EU-065 | Descon - Frack Tank Design Calculation | |
EU-063 | Hazop Study For Fire Water Backup Supply @ Dolphin Energy | |
EU-062 | Al Fowriya - Adequacy Check In Switch Room Floor Slab | |
EU-061 | Descon - Replacement Of Caustic Settler | |
EU-059 | Qg - Descon - New Dc Ups System | |
EU-058 | Qg - Descon - Ten Combined Projects (4 Projects) | |
EU-057 | Qg - Trags - Ten Combined Projects (5 Projects) | |
EU-055 | Qp - Feed For New Csf Security Camera | |
EU-054 | Epic To Provide Fire Water Pumps Tie-In With Tank 171-Tk-006 (Moc 603) | |
EU-053 | Oryxgtl - Epic For Provision Of Drain In U30 Wax & Hc Condensate Reflux Lines (Moc-626) And U35 Dryer Regeneration Gas Recycle To Dryer Feed (Moc-1031) | |
EU-052 | Qp - Lc14101600 - Epic Of 2†High Pressure Flare Pilot Line At Station A4, Ras Laffan | |
EU-051A | Provision Of 33kv Cable Lay Down (Variation 1) | |
EU-051 | Provision Of 33kv Cable Lay Down | |
EU-050 | Qg - Six Combined Projects | |
EU-048 | Two Combined Epc Projects ( Only Project -2 ) | |
EU-046 | Compliance With Qg Procedures For Sampling Of Well Head: Proper Sampling Point In (Qg 3&4 On Shore) | |
EU-044 | Demolition Of Existing Piping And Design, Fabrication & Installation Of New Rtrp Piping | |
EU-043 | Epic For Flare Monitoring & Recording System | |
EU-041 | Design Of 06 N2 Cylinder Quad As Per Bs En 12079 | |
EU-040 | 44" Sea Water Pipe Support | |
EU-039 | Replacement Of Corroded Line In Bog (Q-Chem) | |
EU-038A | Three Combined Projects And Hazop Studies | |
EU-037 | Replace/Repair Defective Portion Of Exisitng Ss 32“ Pumps Barrels Of Dome Roof Lpg Tanks T1&T2 - Tank T2 Under Hold | |
EU-036 | Structural & Piping Modification Works Of Water Line At Direct Reduction Plant No. 1 | |
EU-035 | Replacement Of Bottom Plate Of Stroage Tank | |
EU-034 | 16" Internal Piping | |
EU-033 | Temporary Saddle Support | |
EU-031 | Feed For Installation Of Fo Cable | |
EU-030 | Reused Water Piping Stress Analysis | |
EU-029 | Preparation Of Crane Lifting Drawings | |
EU-028 | Firewater Ring System- Invoice Pending | |
EU-027 | Design Of Foundation & Structural For 10 Tonn Eot Crane-Invoice Pending | |
EU-26A | Waste Heat Boiler Replacement-(Variation 2) | |
EU-026 | Waste Heat Boiler Replacement | |
EU-25A | Provision of Nitrogen Line-(variation 2) | |
EU-025 | Provision of Nitrogen Line | |
EU-024 | Fire Water Pump Test Line Vibration | |
EU-023 | Three Combined Offshore EPC Projects | |
EU-022 | Backwash Water anks | |
EU-021 | Rerating of Coolers | |
EU-020 | Certification of Open Basket | |
EU-019 | Five Combined Projects | |
EU-018 | Replacement of Self Regulating Pressure Control Valve | |
EU-016 | Six Combined Projects | |
EU-015 | Dawing Preparation for Hose Replacement Pipe | |
EU-014 | Al Balagh's New Shed on Street | |
EU-13A | Early Tie-ins for Replacement of ONSAG Pipeline-(variation 2) | |
EU-013 | Early Tie-ins for Replacement of ONSAG Pipeline | |
EU-12B | Piping Vibration and Stress Mitigation-(variation 2) | |
EU-012A | Piping Vibration and Stress Mitigation-(variation 1) | |
EU-012 | Piping Vibration and Stress Mitigation | |
EU-011 | Provision of Isolation Valve | |
EU-010 | Installation of Check Valves | |
EU-009 | Installatin of Compressed Air System | |
EU-008 | Installation of ESD Push Button | |
EU-007 | Designing of Steel Structures for Double Storey Drivers | |
EU-006A | Replacement of Sea Water Fire Pumps and Refurbishment of Fire Fighting systems-(variation) | |
EU-006 | Replacement of Sea Water Fire Pumps and Refurbishment of Fire Fighting systems | |
EU-005 | Designing of Pipe Support Structure and Foundation design | |
EU-004 | Designing of Tanks | |
EU-003 | Upgradation of Air Compressor | |
EU-002 | Modification of Transfer Conveyer Bridge | |
EU-001 | Pipe Support Modification (2 nos) |